Monitoring is an integral part of the programme. It allows us to ensure projects stay on track and take action if projects are not performing. Continued Government funding depends on agreed targets being met.
All projects will be monitored quarterly against figures in the Delivery Schedule; this is the responsibility of the Project Manager at the Delivery Partner organisation. Completed forms should be returned to the Evaluation Manager by the deadlines below.
| Year |
Quarter |
Required Return |
Deadline |
| 2007 / 08 |
Quarter 1 |
All monitoring information for April - June 2007 |
16/07/2007 |
| 2007 / 08 |
Quarter 2 |
All monitoring information for July - September 2007 |
15/10/2007 |
| 2007 / 08 |
Quarter 3 |
All monitoring information for October - December 2008 |
14/01/2008 |
| 2007 / 08 |
Quarter 4 Interim |
Actual expenditure January – February 2008 and projected expenditure March 2008 |
03/03/2008 |
| 2007 / 08 |
Quarter 4 |
All monitoring information for January - March 2008 |
14/04/2008 |
We expect delivery partners to report on:
- Finance
- Outputs
- Milestones
- Summary of Progress and Asset Register
|